This civil construction project involved several key tasks encompassing the installation of reinforced concrete elements, formwork supply and installation, reinforcement fixing, and concrete placement (FRP), along with associated in-situ concrete works like deck/base slabs, apron slabs, headwalls and Stairs.

Through these meticulously executed tasks, the civil construction project progresses towards its completion with a solid foundation with essential infrastructure in place on time and on Budget.

Scope:

• Installation of Concrete base and fauna shelf

• Installation of precast concrete box Culverts

• Install of in-situ wing and head walls

• Form up and pour in-situ stairs

• Install in-situ concrete Pedestals

• Install railing

Project Stats:

  • Concrete: 370m³

  • Reinforcement: 18T

  • Operational Capacity: 5