Completion - 2021

The Terminal comprises more than 150,000 tons of sand fill and 1,200 cubic meters of concrete. Strategically situated to tie into the existing 330kV Mid-West Transmission Line, its location was meticulously selected to minimise environmental impact by utilising pre-existing cleared spaces.

Supersett collaborated closely with Western Power to devise an accelerated schedule, ensuring timely completion within stringent deadlines.

Project Stats:

  • Concrete: 1,280m³

  • Reinforcement: 52T

  • Operational Capacity: 20