Client Project Timeline Location
Western Power March to April 2014 West Kalgoorlie

This contract was to refurbish an 11kv switch room and control room at west Kalgoorlie substation due to damaged caused by a switchboard catching fire.

Job included;

  • cleaning and tinting existing internal face brickwork
  • remove existing ceiling and replace with new fire rated ceiling
  • new automated air conditioning system
  • remove all doors and door frames and replace with new 120/120 fire rated doors and door frames 
  • removal of all existing electrical fixtures and cabling and replaced with new.