Rockingham Substation

Rockingham Substation
Client Project Timeline Location
Western Power January 2014 to June 2014 Rockingham

This contract is to upgrade the existing chainmesh fence build a 340m long tilt panel boundary fence and 2 motorised sliding sound proof gates.

Also in the contract is to build 3 tilt panel blast walls between the three existing 132kv transformers. This has meant building a new bund around one of the existing transformers while it remained in service to incorporate the footings for the new blast walls. Also part of this project was to remove hydrocarbon contaminated soil and validate the area.